Enercon Wind Turbines: Energiequelle Starts Construction of The 21 MW Wind Farm In Teschendorf

Teschendorf, Germany - Construction of the wind farm has now begun in Teschendorf, Lower Saxony. Energiequelle GmbH, which planned and developed the wind farm in the district of Gifhorn, is erecting five Enercon E-138 turbines with a hub height of 130 metres and an output of 4.2 MW each.

The wind farm has a long planning period behind it, as the regional planning of the Greater Braunschweig Regional Association (RGB) took almost ten years, with the subsequent development plan procedure taking another two years. Only then were the regional planning and land-use planning requirements for the wind farm met in order to initiate the authorisation procedure for the wind farm. Energiequelle was then able to obtain the authorisation within nine months.

The wind farm is scheduled to be commissioned in October 2025. The annual electricity yield is estimated at around 60 million kWh. Energiequelle will be responsible for the technical and commercial management of the wind farm.



Source: IWR Online, 26 Jun 2024

 