RWE and KKR Secure Record Financing for British Offshore Wind Farms Norfolk Vanguard West and East
Essen/London – Energy company RWE and US financial investor KKR have completed financing for two offshore wind farms in the UK with a combined capacity of around 2.8 GW. The investment volume for Vanguard West and Vanguard East, including grid connection, is around GBP 12 billion. Full commissioning is planned for 2030.
35 Banks Finance Offshore Wind Projects – KKR Takes 50 Percent
RWE and KKR have secured a consortium of 35 international banks to finance the two offshore wind farms. The financing package totals GBP 12.8 billion, of which GBP 11.1 billion are term loans and GBP 1.7 billion are ancillary facilities. According to RWE, it is the largest project financing for offshore wind energy in the UK to date.
The UK National Wealth Fund has committed GBP 1 billion. The financing is also supported by German federal export credit guarantees (Hermes cover) and backing from the Danish export credit agency EIFO.
RWE and KKR have also completed the ownership transaction announced in January 2026. KKR now holds 50 percent each in Vanguard West and Vanguard East. Both partners are providing equity. RWE is leading project delivery on behalf of the joint venture.
The transaction also has implications for RWE’s balance sheet. Following the nine-month figures published on November 11, the company expects its net debt to fall from EUR 17 billion at the end of September to around EUR 12 billion by year-end 2026. RWE cites the deconsolidation of the Vanguard projects as the main reason.
Offshore Construction Scheduled to Start in Early 2027
The wind farms are being built around 50 to 80 kilometres off the coast of Norfolk in the North Sea. In the British auction round, a combined 3.09 GW was awarded to the two projects. In practice, RWE is currently planning with an installed capacity of around 1.4 GW each, or 2.8 GW in total. According to the company, together they could on paper supply electricity to around three million British households.
Onshore cable work and the construction of the substations are already well advanced. Offshore construction is scheduled to begin in early 2027. The first foundations for Vanguard West are planned for the first half of 2027, followed by Vanguard East.
British Offshore Auctions: Higher Price Caps After Zero-Award Round in 2023
Vanguard West and Vanguard East are among the offshore wind projects that received awards under changed conditions after the unsuccessful British auction round in 2023. In the seventh auction round (AR7) in January 2026, both projects secured inflation-indexed Contracts for Difference (CfD) with a term of 20 years and an award price of GBP 91.20 per MWh in 2024 prices.
In total, around 8.4 GW of offshore wind capacity was awarded in AR7, including around 8.2 GW for fixed-foundation projects. The British government had raised the administrative maximum prices following the unsuccessful 2023 auction, after rising project costs had weighed on the economic viability of new projects.
British Offshore Wind Market: Wide Gap Between Expansion Forecast and Government Target
With its Clean Power 2030 Action Plan, the British government aims to cover at least 95 percent of electricity generation in the UK with climate-friendly energy sources by 2030. The government plan provides for offshore wind capacity to be expanded to between 43 and 50 GW.
According to the European wind energy association WindEurope, around 17.6 GW of offshore wind capacity was connected to the grid in the UK at the end of June 2026. In the first half of 2026, 620 MW was added. WindEurope’s current forecast puts offshore wind capacity at around 30 GW by 2030.
The expected expansion therefore falls well short of the political target. Financial close for the two Vanguard wind farms with a combined 2.8 GW shows the scale individual projects have now reached. To meet the British expansion targets by 2030, however, significantly more of the already planned offshore wind projects would have to be financed, built and connected to the grid within a few years.
Source: IWR Online, 16 Nov 2026