365 Metres: World's Tallest Wind Turbine Generates Power – Gicon Plans Series Production from 2030

Schipkau, Germany – At 365 metres, the world's tallest wind turbine has been officially commissioned in Schipkau in the German state of Brandenburg and is generating electricity. Developed by Dresden-based engineering company Gicon, the turbine has a hub height of 300 metres and is intended to pave the way for the commercial use of wind at higher altitudes. Gicon is already planning five more turbines.

Harnessing the wind resource at a height of 300 metres opens up the prospect of significantly higher electricity yields for onshore wind energy. Of particular interest is the possibility of making more intensive use of existing wind farm sites by adding turbines that operate at greater heights. Practical operation and further industrialisation will have to show whether the expected yield gains can be realised economically.

World-Record Wind Turbine with 300-Metre Hub Height Connected to Grid

Gicon's new wind turbine in Schipkau has a hub height of 300 metres and reaches a total height of 365 metres. According to Gicon, this makes it the world's tallest wind turbine. The prototype has an installed capacity of 3.8 MW. Gicon developed the high-altitude wind tower concept, which was implemented on behalf of Beventum GmbH, a subsidiary of the Federal Agency for Breakthrough Innovation (SPRIND).

The technology is based on a steel lattice structure with a telescopic inner tower. A special strand-jack lifting system raises the inner tower to its intended height within the outer support structure. The tower thus carries out much of the lifting required for its own erection.

The pilot project reached an important milestone with its official inauguration on November 19, 2026. The experience gained from construction and operation is now intended to support further technical development and preparations for additional projects.

Wind Measurements Show 63 Percent Higher Yield Potential

A joint analysis by Gicon, Beventum and SPRIND based on wind measurements at the Klettwitz site shows the additional yield potential offered by wind at higher altitudes. The study is based on met mast and lidar data jointly analysed for the period from April 2023 to April 2024.

At a height of 300 metres, the met mast recorded a mean wind speed of 8.51 m/s, compared with 6.66 m/s at 150 metres. The average wind speed was therefore around 28 percent higher at the greater height.

Using the met mast data, the project partners calculated a gross annual electricity yield of 36.6 GWh for a modelled 9.5 MW wind turbine with a hub height of 300 metres. At 150 metres, the figure would be 22.4 GWh. This corresponds to a calculated additional yield of 63.4 percent. The results highlight the considerable yield potential of high-altitude wind technology at the site studied.

Gicon Plans Five More Turbines and Series Production

Following commissioning, Gicon aims to further develop and commercialise its high-altitude wind technology. The company says it plans to build five more high-altitude wind towers. According to Jochen Großmann, Founder and Managing Director of Gicon, letters of intent for the construction of 100 turbines in Germany are also already in place.

Series production is scheduled to begin no later than 2030. For this, Gicon is counting on cooperation with local small and medium-sized companies. The company expects improved construction methods and series production to reduce costs.

For future high-altitude wind towers equipped with wind turbines of 8 MW or more, Gicon forecasts annual electricity yields of 30 to 33 GWh. As its economic target, the company cites a levelised cost of electricity (LCOE) of less than 5 euro cents/kWh.

High-Altitude Wind Could Complement Existing Wind Farms

Another approach to the commercial use of the new design is the integration of particularly tall wind turbines into existing wind farms. According to SPRIND's preliminary estimates of the potential, up to 4,000 high-altitude wind towers could be built in Germany in this way.

High-altitude wind technology could thus unlock additional power generation capacity without requiring the development of new wind farm sites on the same scale. This would require suitable wind conditions, technical integration into existing wind farms and economically viable investment costs.

The wind measurements already provide concrete indications of considerably higher yields at greater heights. Operating experience and the further development of high-altitude wind technology will show whether the expected yield gains can also be exploited economically.



Source: IWR Online, 27 Nov 2026

 