Brussels - The build-up of a European hydrogen economy is progressing, but remains well below expansion plans. According to the new monitoring report by the EU energy regulatory agency ACER, electrolyser projects with a combined capacity of 4.2 GW were already operating, under construction or had reached a final investment decision as of September 2026.
Electrolyser Deployment in the EU Lags Behind Targets
At the end of 2025, around 490 MW of electrolyser capacity was actually in operation in the EU. Installed capacity had thus increased almost sixfold compared with 2020. By September 2026, operating capacity rose to around 510 MW. The far larger share of the 4.2 GW recorded by ACER is accounted for by plants under construction or projects with a final investment decision.
For 2030, various European scenarios and national hydrogen strategies assume electrolyser capacity of between 30 and 58 GW. The gap between the project volume realised so far and the long-term expansion plans therefore remains substantial.
Hydrogen in the EU is still produced predominantly by other methods, in particular steam reforming of natural gas. Electrolysers account for less than one percent of total hydrogen production capacity. Production capacity stood at around 10 million tonnes per year in 2025, while demand was 7.3 million tonnes. Electrolyser deployment therefore serves not only to meet additional demand but, in particular, to replace existing fossil-based hydrogen production.
Refineries and Steel Industry Shape Investment
The secured electrolyser capacity is concentrated in a few industrial applications. Refineries account for around 2.1 GW, or 49 percent of the 4.2 GW. European requirements for renewable fuels, along with penalties for non-compliance, create incentives to replace fossil-based hydrogen.
The steel industry follows with around 1.2 GW. However, the allocation of electrolyser projects does not yet mean secured hydrogen offtake: some steel projects could initially use natural gas. For ammonia and methanol production, by contrast, only around two percent of secured electrolyser capacity each is recorded. According to ACER, no commercial EU project for synthetic aviation fuels has so far reached a final investment decision.
High production costs remain a central challenge for the market ramp-up. Renewable hydrogen is so far considerably more expensive than hydrogen produced conventionally from natural gas. In European hydrogen support auctions, project developers in Spain put production costs for electrolytic hydrogen at around EUR 5.3 per kg. Public support is contributing to the build-out of larger electrolyser capacity in the EU. The 15 largest electrolyser projects with a final investment decision, with a combined capacity of around 3 GW, have received funding from European or national support programmes.
Hydrogen Pipelines: Germany at the Centre of Deployment So Far
A large gap remains between planning and implementation of the European hydrogen pipeline network. ACER records pipeline projects totalling around 42,000 km at various stages of development, including numerous projects not yet decided. According to ACER, around 622 km of hydrogen pipelines were commissioned across the EU in 2025 and 2026. A further 555 km were under construction.
Germany is a focal point: ACER cites around 590 km of newly commissioned pipelines in 2025 and 2026, and about 480 km under construction.
For imports, too, binding or otherwise secured offtake volumes are limited. For projects scheduled to start by 2030, ACER puts them at 0.17 million tonnes of hydrogen equivalent per year.
International Comparison Shows Different Conditions
According to the International Energy Agency (IEA), more than 60 percent of the electrolyser capacity worldwide that is already in operation or secured in the implementation phase is located in China, and less than 20 percent in Europe. At the same time, Europe accounts for around 45 percent of the corresponding investment. ACER sees this as an indication of higher investment costs per unit of capacity in Europe.
Further European ramp-up is likely to focus initially on industrial applications with reliable demand and suitable infrastructure. ACER stresses the importance of clear regulatory frameworks and long-term sales prospects for additional investment.